Proposed for future working parties.

This is also the de facto Job List. The distinction between Lesser and Major tasks is simply whether it can be completed whilst the Space is open without major disruption to the users, not time or effort required. If you wish to help, pick something from Lesser and get stuck in!


Major Tasks

  • Improve lighting
  • Inventory list to be created
  • Lay a false/drop ceiling to keep heat at a useful height. Materials need discussion and then sourcing.
  • Put the insulation in the workshop somewhere more useful.
  • (Re)wire the kitchen. [In progress!]
  • And presumably some gap filling and then painting would be required.
  • We also need to paint more of the ceiling.
  • The Workshop is pretty musty from condensation under the roof. We need to work out some long-term solution to this. [Double glazing has been costed for grant purposes, roof insulation and ventilation fan pending.]

Lesser Tasks

  • Set up the kitchen cabinets once the kitchen wiring/decor state allows it. [This is now in progress]
  • Expand the user box racks to include more bays - we're out of space! [Nearly completed!]
  • LED light needs installing in workshop on the CNC side.
  • Fix / calibrate 3D printers 3 and 4. [Steve has been fiddling aggressively with #4 and square things have been sighted. We await further news.]
  • Fiddle with the stair light sensor to make it more helpfully ranged. Currently it will operate when you are already halfway up the stairs, or already on the balcony whilst nightblind from leaving the Space.
  • Fix the main door closer. Trying to lock up in a high wind is ... challenging.
  • Upgrade front door camera.
  • Acquire and deploy a cooker. (The breakfast maker doesn't count - we're not cooking for ants.)
  • Workshop dust management system. Cyclone separator and blastboxes are complete, the hosing and gate relays are now in progress. All hoover hose donations are much appreciated.
  • Make another Cyclone, additional hoover pending since pipe friction gives rapidly diminishing returns with the available horsepower. Curse you, physics!
  • A spray booth is on the cards, as we have another extractor fan now.
  • Fix concerningly squeaky workshop hatch.
  • Workshop tool rack. Pegboard based perhaps?
  • Wood storage system, ideally on casters. Currently the idea is for something like the illicit lovechild of these two - to this end we also need more pallets and scrap wood. Also casters. [Woodzilla is now in progress, you may have noticed the subtle presence in the workshop. It's the thing that looks like a battering ram / triple decker coffin on wheels.]
  • Clean and deploy the drawers somewhere sensible.
  • Sort & assess the supplies / materials / inventables / debris on the workshop racking. Possibly some of these articles could then go in the drawers.
  • We have a brand new toilet and a not-so-new shower tray surplus to requirements. They need extracting, photographing and listing somewhere like Gumtree or Ebay.
  • Close the roof windows in a lasting fashion. Steve has been going up and down the ladder like a demented yo-yo thanks to the recent gales providing us with impromptu ventilation.
  • Fix the doorbell - it seems to work 80% of the time, when it feels like it, only if it's completely dry, and there is not a full moon. Usually.
  • Fix the cold tap in the toilet
  • Potential grants need research and chasing. There are many options here so lots of people can help out.
  • Paperwork, some pertaining to the above. Health and Safety Policy (drafted, awaiting feedback) , risk assessment updates (addendum drafted, awaiting feedback) , power tool usage policy (first draft/idea stage, awaiting feedback)

Complete

  • Laser chores; test & prove to seller that the PSU popped, install cutout switch, ammeter [Group effort]
  • Install micro guttering or a wicking drainage system to stop the Workshop condensation from dripping randomly. If it absolutely must drip it needs to do it in an orderly fashion! [Created by Adam; field test results positive!]
  • Fix the bench power supply [Group effort]
  • Labels for the various anonymous tool boxes (Adam)
  • Rack for storage boxes (Martin)
  • The Workshop Door (Adam & Jon).
  • Fit curtains (Rails, nets and curtains)
  • Fit lock to second room
  • Move the cupboard/contents from the church
  • Run wired network to main tables Network
  • Fit doorbell
  • Install permanent sign
  • Install our own wireless AP (one AP installed, thanks Phil)
  • Work bench for soldering, 3D printing etc, to be built and installed to room one
  • Setup Raspberry Pi work station
  • Projector stand
  • Projector screen